As part of the council’s proactive plan to prepare the city’s highway network for the future, Roebank roundabout, in Kingswood, has been identified as a priority site for improvement.
It is anticipated that traffic volumes in this area will increase in the years ahead.
The current roundabout acts as a pinch point, causing congestion and delays to journey times.
A scheme has been designed to increase capacity at the roundabout, with the aim of reducing congestion and improving journey reliability while also enhancing safety and active travel facilities for pedestrians and people cycling.
The scheme includes -
- converting the existing roundabout into a signal-controlled roundabout, improving traffic management and enabling more efficient operation of the junction
- enhancing walking and cycling infrastructure, including new toucan crossings and segregated off-road cycle routes to provide safer and more accessible connections
- improving safety by introducing signal-controlled crossing facilities on all approaches to the junction, allowing pedestrians and cyclists to cross safely where some arms currently have either no crossing provision or unsignalised facilities
- widening the carriageway to provide additional traffic lanes and increasing the network capacity, helping to reduce journey times and queuing
- selectively removing some trees to facilitate widening works, with replacement planting at a ratio of two new trees for every one tree removed
- resurfacing the carriageway and footway to improve their condition, durability and long-term performance.
Roebank Roundabout Capacity Improvement Scheme Latest Developments
From Monday 2 November 2026, a six-week public engagement exercise was launched to get feedback from residents, businesses and commuters on the proposals.
Have your say on the Roebank roundabout project
You will be able to attend one of the drop-in sessions that will be announced in November.